Carrigtwohill Flood Relief Scheme
Construction and upgrade of an existing flood mitigation project for the IDA, involving extensive planning to ensure no works had any operational impact to users of the existing business park.
3.74
Million Project Value
8
Month Project Value

Project Overview

The Carrigtohill flood mitigation project was undertaken for the IDA to allow expansion of the current IDA Business Park, located in Cork. The current business park has tidal AADT’s of over 3,000 in peak hours and has a high pedestrian footfall. All works had to be completed in a restricted confined space to ensure there was no disruption to the business park users. Temporary traffic management phasing was fundamental for the successful delivery of the project. To ensure pedestrian access, which had to remain open at all times, several temporary footpaths where installed during the project.

Extensive earthworks were undertaken, which included the excavation of over 100,000m³ for the attenuation pond and attenuation tank, and disposal off-site of over 50,000m³. Silt mitigation measures were implemented to prevent silt from entering the adjacent stream and prevent rainwater entering the excavation. The project also involved the importation of over 1,000m³ of sand for the base of the crated attenuation system and of bulk drainage materials.

Over 3,000m³ of dredged material was excavated from two existing storage ponds to remove the silt build up. The dredged material was stored on-site within a bunded area to allow the material to dry out before being disposed of off-site. Strict environmental controls were implemented during the dredging works. This included over pumping the existing stream feeding the pond, allowing the pond to drain prior to undertaking the works. Three six-inch pumps were installed, along with one six-inch standby pump.

Works also included levelling the surrounding area with surplus topsoil to remediate the hollows that were causing ponding and, subsequently, isolated flooding. A new storm water drainage pipe, 1.5m in diameter and in excess of 4m deep, had to be laid up the east road within the IDA Business Park. The new storm alleviation overflow pipe of 1.5m diameter that was installed crossed an existing 900mm long water main. Following careful excavation and exposing the line and level of the existing water main, it was concluded that the new pipe could not be installed due to insufficient clearance and the risk of damaging the service. It was, therefore, proposed that the 1.5m single pipe would be replaced with two 900mm pipes, which would allow easier construction and more clearance beneath the existing water main. This proposal was accepted by the client and Irish Water and used in the final works.

Key Features

  • Site clearance and bulk excavation
  • Extensive temporary traffic management
  • Service investigation, trial holes, temporary works and service protection
  • Extensive temporary works to maintain road access at all times
  • 774m³ embankment construction
  • Construction of a new 49,223m³ attenuation pond and associated flow / hydro brake control headwalls
  • Construction of new 11,440m³ attenuated crate storage system
  • 919m of 1.5mØ concrete overflow pipe and outfall up to 5m deep
  • Trash screen upgrades and the installation of several non-return valves
  • Landscaping including top soiling, grass seeding and shrub planting etc. (28,000m²)
IDA
Project Team
Client:
IDA
Quantity Surveyor:
ByrneLooby
Structural Engineer:
ByrneLooby
Project Details
Contract Value:
€3.74
Duration:
8 Months