Data Centre Gas Generation Station
Construction of a 5,000m² gas generation building and compound, including 1.5MW gas generators, 3MW containerised diesel generation sets, and 400V to 20kV transformers
16000
Square Metres
€20
Million Project Value
5
Month Project Duration Project Overview
The project involved the construction of a 5,000m² gas generation building and compound, including twelve 1.5MW gas generators, two 3MW containerised diesel generation sets, and seven 400V to 20kV transformers.
We also installed specialised high-performance acoustic wall panelling to the full external envelope of the building and ensured it was integrated with the existing utilities and data hall infrastructure.
Works also included the full coordination and integration of BENI and client-direct vendors.
Key Features
- 320 tonnes of steel
- 2,850m² of high-performance acoustic cladding (noise reduction level of 32dB)
- Successful start-up and IST with existing data hall infrastructure and equipment
Project Team
Client:Confidential
Architect:
Confidential
Quantity Surveyor:
Confidential
Structural Engineer:
Confidential
M&E Consultant:
Confidential
Project Details
Contract Value:€20 Million
Floor Area:
16,000m²
Duration:
5 months